This page will provide a weekly update of public works projects and their corresponding impacts to help keep disruptions to our citizens lives as minimal as possible.

For the Week of August 8, 2016

Roads:


• Burlington between Continental and Burlington Bridge - Paving - Road will be closed as each section is completed;
• Bike Lane Signs will be installed throughout the Flats to accompany newly painted Sharrows;
• East of Montana and South of Platinum - Street Sweeping;
• Between Harrison and Continental, and South of Shields Street – Street Sweeping;
• Upper West Side, West of Clark - Flushing; and
• Copper Mountain Park - Sweeping.

Water Utility:


• Harrison Ave and Holms – Water Main Project is complete (two weeks ahead of schedule);
• Thomas Avenue and Evans Street – Valve installation – roads will be open with traffic control measures; and
• Meadow Brook Drive – Mobilization and preparation work for pipe replacement – road will be open with traffic control measures.

Metro Sewer:

• Aluminum Street - Sewer replacement, Road closed from Montana to Main;
• Aluminum and Main Street - Manhole replacement - road will be open with traffic control measures;
• Steel Street – Sewer Installation – Road closed from Ophir to Mining Museum Road; and
•Granite and May Street extension – Please expect the following closures, which will last two to three weeks. Butte-Silver Bow will provide updates if necessary:
-The Intersection of Granite and Ophir;
-The intersection of Park Street and Mining Museum Road
-Montana Tech Road and Mining Museum Road; and
-The North Entrance to the Natural Resource Building.

NorthWestern Energy Updates:

• Prep for paving in the alley south of Caledonia Street, between Henry Street and Excelsior Avenue;
• Complete new gas service line tie-overs in the alley south of Caledonia Street, between Excelsior Avenue, and Alabama street – Alabama Street will remain open;
• Continue tying over new natural gas service lines in the alley south of Woolman Street between Henry Street and Excelsior Avenue;
• Begin installation of new natural gas main in the alley south of Antimony Street, between Henry Street and Excelsior Avenue;
• Begin installation of new natural gas service lines in the alley south of Antimony Street, between Emmett and Henry Streets; and
• Continue installation of new natural gas main and service lines in Quartz Street, between Alabama and Crystal Streets – Quartz Street will remain closed for the completion of this project.


For the Week of August 1, 2016


Roads:


• Montana between Boardman and Center – Paving – road will be closed as each section is worked on;
• Idaho between Montana and Missoula - Paving, road will be closed as each section is worked on;
• Cobban - Lafayette to Kaw Street painting (sharrows);
• Texas Ave. - Cobban to Shields – Street painting (sharrows);
• Kaw – Street painting (sharrows);
• Street Sweeping and Flushing – East of Montana and South of Mercury; and
• Street Sweeping and Flushing – Between Texas and Continental and South of Shields.

Water Utilities:

• Harrison Ave and Holms – Water Main Project, traffic will remain two lanes, traffic will use the northbound lanes (east side of Harrison Ave.) project is in the third of three phases, with an anticipated completion date of August 19. All business are open and can be accessed

Metro Sewer:

• Aluminum Street – Sewer replacement, Road closed from Montana to Main; and
• Granite and May Street extension – Please expect the following closures, which will last two to three weeks. Butte-Silver Bow will provide updates if necessary:
-The Intersection of Granite and Ophir;
-The intersection of Park Street and Mining Museum Road
-Montana Tech Road and Mining Museum Road; and
-The North Entrance to the Natural Resource Building.